Conditions as hard as rock
After the opening of Eismeer station, the construction of the Jungfrau Railway runs into difficulties. There ia a lack of money. Not least because the construction management changes Guyer-Zeller's original plans and, instead of the Jungfrau summit, plans the Jungfraujoch as sea level at 3,454 metres above sea-level. Despite this change to the plans, the construction does not go so well. The rock provides more resistance than expected; in summer, the profitable passenger transport has priority and, in winter, the water used to produce the power for the railway and machines in the valley runs dry every now and again. In addition, the working conditions wear out the workers, causing a high turnover of staff and leading to worker conflicts. The workers strike six times, the construction management changes eight times and 30 construction workers pay with their lives, usually due to blasting accidents. The employers attempt various measures to create a better mood, for example with a guaranteed bottle of red wine per worker per day.